PENERAPAN METODE EARNED VALUE ANALYSIS MENGGUNAKAN SOFTWARE PRIMAVERA PROJECT PLANNER PADA PEMBANGUNAN INSTALASI PENGOLAHAN AIR LIMBAH

Nadila Agnessia(1*), Drajat Indrajaya(2)

(1) Program Studi Teknik Industri, Fakultas Teknik dan Ilmu Komputer, Universitas Indraprasta PGRI, Jl. Nangka Raya No. 58 C, Tanjung Barat, Jagakarsa, Jakarta Selatan
(2) Universitas Indraprasta PGRI
(*) Corresponding Author

Abstract


PT Gasd Geosby Indonesia is a company engaged in environmental services and construction. PT Gasd Geosby Indonesia is handling a Wastewater Treatment Plant (IPAL) construction project in Cikarang for an industrial company. The project experienced delays due to several factors supporting activities. Factors that can affect delays include people, materials, costs, and the tools used. Delay cannot be avoided but can be controlled. One form of project control is to calculate the project completion time and the amount of costs that will be incurred until the project is completed. One of the methods used to estimate the time and cost of the project according to the budget according to the work that has been completed is Earned Value Analysis (EVA). The result of data processing using the Primavera application is Estimate At Completion (EAC) in the 4th week of Rp. 185.682.084, the estimated cost is greater than the project planning cost of Rp. Rp. 147.794.994 if the trend of project implementation during the visit did not change until the end of implementation. From the data obtained based on the results of the field visit at week 4, the estimated completion of the project for 43 days or 14 days from the last day of visit was obtained.

Full Text:

PDF

References


B. Santosa, Manajemen Proyek Konsep dan Implementasi. Yogyakarta: Graha Ilmu, 2018.

D. A. Widayanti, W. Hartono, and Sugiyarto, “Pengendalian Biaya Dan Waktu Dengan Menerapkan Metode Earned Value Analysis ( EVA ) Menggunakan Software Primavera Project Planner P6,” Matriks Tek. Sipil, vol. 6, pp. 1457–1464, 2017.

M. Priyo, Metode “Earned Value” Pada Jasa Konstruksi, vol. 53, no. 9. Yogyakarta: Lembaga penelitian dan Pengembangan Pendidikan Universitas Muhammadiyah Yogyakarta (LP3 UMY), 2012.

M. Priyo and T. Zhafira, “Penerapan Metode ‘Earn Value’ Dan ‘Project Crashing’ Pada Proyek Konstruksi: Studi KasusPembangunan Gedung IGD RSUD Sunan Kalijaga, Demak ,” Semesta Tek., vol. 20, no. 1, pp. 29–50, 2017.

D. Apriyanto, “PENERAPAN PROGRAM PRIMAVERA 6.0 UNTUK MENGANALISIS KONSEP NILAI HASIL (Studi Kasus Proyek Pembangunan Kantor Polres Purworejo) SKRIPSI,” Universitas Muammadiyah Purworejo, 2016.

S. Sandhya and N. Ganapathy Ramasamy, “Analysis of Project Performance Using Earned Value Analysis,” Int. J. Sci. Eng. Technol. Res., vol. 4, no. 4, pp. 1080–1085, 2015.

F. Ramdhani, “Analisis Bi Aya Dan Waktu Dengan Metode Earned Value Concept Pada Proyek Bjdm Area Rl Construction At Well 3S-21B Area 9 Pt. Adhi Karya Cs Work Unit Rate Packagea – Duri,” J. Tek. Sipil Univ. Abdurrab, vol. 1, no. 01, pp. 17–35, 2016.

S. Nugroho, D. Pujotomo, and I. Z. Purwanto, “Analisis Performansi Pekerjaan Proyek Pembangunan Mechanical – Electrical – Pumbling Gedung Sentraland Semarang Menggunakan Metode Earned Value Analysis,” J. Tek. Ind. Fak. Tek. Univ. Diponegoro, pp. 1–11, 2016.

E. Wahyuni and B. Hendrawan, “ANALISIS KINERJA PROYEK ‘Y’MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (Studi Kasus di PT Asian Sealand Engineering),” J. Appl. Bus. Adm., vol. 2, no. 1, pp. 60–78, 2018.

Y. W. Nufah, G. Yanti, and F. Lubis, “Analisis Proyek Dengan Metode Earned Value Concept (Studi Kasus Pada Proyek Pembangunan Jalan Tol Ruas Pekanbaru – Dumai Seksi 2 STA. 9+500 - 33+600),” Semin. Nas. Cendekiawan ke 5 Tahun 2019 Buku 1 ”Teknologi dan Sains“, vol. 1, pp. 1–7, 2019.

S. Soltan and M. Ashrafi, “Predicting project duration and cost, and selecting the best action plan using statistical methods for earned value management,” J. Proj. Manag., vol. 5, pp. 157–166, 2020, doi: 10.5267/j.jpm.2020.3.002.

H. Ashad, L. B. Said, and U. D. Hardi, “Penerapan Metode Analisis Nilai Hasil Terhadap Biaya Dan Waktu Pelaksanaan Proyek (Studi Kasus Pembangunan Atc Tower Bandar Udara Syukuran Aminuddin Amir, Di Luwuk),” Open Sciense Framew., vol. 3, no. 2, pp. 101–110, 2020.

V. Abma, “Analisis Pengendalian Waktu Dengan Earned Value Pada Proyek Pembangunan Hotel Fave Kotabaru Yogyakarta,” J. Tek. Sipil, vol. XXI, no. 2, pp. 218–228, 2016.




DOI: http://dx.doi.org/10.30998/faktorexacta.v15i1.10456

Refbacks

  • There are currently no refbacks.




Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.

DOAJ faktor exacta Garuda ISSN BRIN sinta

Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.

Flag Counter

site
stats View Faktor Exacta Stats


pkp index